My project

Full renovation, 85 m² flat

Property: Madrid, Chamberí (example) · Last updated: 30 Oct 2026

Your private project area. Please don't share this link.

Project stages

  1. Structure7 Sept 2026 – 25 Sept 2026
    Done
  2. Electrics28 Sept 2026 – 9 Oct 2026
    Done
  3. Plumbing12 Oct 2026 – 6 Nov 2026
    In progress
  4. Finishes9 Nov 2026 – 4 Dec 2026
    Pending
  5. Fittings and light7 Dec 2026 – 18 Dec 2026
    Pending

Site photos

  • Strip-out finished
    Week 1 · Strip-out finished
  • New partition walls up
    Week 3 · New partition walls up
  • New electrics in every room
    Week 5 · New electrics in every room
  • Bathroom and kitchen pipes
    Week 7 · Bathroom and kitchen pipes

Payment schedule

Contract signature1 Sept 202612,000 €Paid
Structure and services finished6 Nov 202618,000 €Pending
Finishes completed4 Dec 202614,000 €Pending
Key handover18 Dec 20266,000 €Pending